Village of Lindenhurst v. J.D. Posillico, Inc., 21 N.Y.3d 1024 (2013)
A cause of action for defective construction, even when brought as a claim of continuing public nuisance by a third-party beneficiary to the construction contract, accrues upon completion of the construction work for statute of limitations purposes.
Summary
Ten related actions were brought by municipalities against contractors alleging faulty workmanship in sewer construction performed decades earlier, causing damage to roadways. The municipalities claimed the faulty work constituted a continuing public nuisance. The New York Court of Appeals affirmed the dismissal of the actions as time-barred, holding that the claims, even if characterized as continuing public nuisance, arose from defective construction and accrued upon completion of the work. The court applied the rule from *City School Dist. of City of Newburgh v Stubbins & Assoc.*, extending it to third-party beneficiaries who are not strangers to the contract, and also rejected the argument that the ongoing damage constituted a continuing tort.
Facts
In the 1970s and 1980s, Nassau and Suffolk Counties contracted with various construction companies (the defendants) to build a sewer system. The contracts included “protection clauses” requiring the contractors to restore roadways to their “usual condition” post-construction, as per County Law § 263. After the sewer construction was finished, the areas surrounding the sewer lines settled, leading to damage to adjacent roadways, sidewalks, and curbs within the plaintiff municipalities.
Procedural History
In July 2009, ten municipalities filed separate actions against the contractors, alleging a continuing public nuisance due to faulty workmanship. The Supreme Court dismissed each complaint, and the Appellate Division affirmed, holding the actions were time-barred under the six-year statute of limitations for breach of contract (as the claims were viewed as third-party beneficiary claims). The Court of Appeals granted leave to appeal and affirmed the Appellate Division’s decisions.
Issue(s)
1. Whether a claim by a third-party beneficiary against a contractor for faulty workmanship in construction accrues, for statute of limitations purposes, upon completion of the construction, even when framed as a continuing public nuisance?
2. Whether the continued presence of roadway defects resulting from the contractor’s alleged negligence constitutes a continuing tort that gives rise to successive causes of action?
Holding
1. Yes, because the essence of the claim arises out of defective construction, and under City School Dist. of City of Newburgh v Stubbins & Assoc.*, such claims accrue upon completion of performance, regardless of how the claim is characterized.
2. No, because the tortious conduct consisted of discrete acts (negligent excavation and backfilling) that ceased upon completion of the sewer construction, and there was no unlawful encroachment or continuous interference with property easements.
Court’s Reasoning
The Court of Appeals relied on the precedent set in *City School Dist. of City of Newburgh v Stubbins & Assoc.*, 85 N.Y.2d 535 (1995), which established that in cases against contractors, the statute of limitations begins to run upon completion of the contractual work. The court stated, “In cases against architects or contractors, the accrual date for Statute of Limitations purposes is completion of performance.” The court reasoned that the municipalities’ claims, though framed as continuing public nuisances, were fundamentally based on the contractors’ alleged breach of duty under the construction contracts’ protection clauses. The court emphasized the language in the complaints where the municipalities specifically alleged that the defendants “committed faulty workmanship under said contracts.” The Court extended the *Newburgh* rule to third-party beneficiaries, noting that the counties contracted with the defendants to install the sewer system for the benefit of the municipalities.
The Court rejected the municipalities’ attempts to distinguish *Newburgh*, stating that the rule is not limited to owners of real property and that the counties’ intention to retain ownership of the sewer lines did not diminish the municipalities’ status as intended beneficiaries. The Court also dismissed the argument that the municipalities’ lack of involvement in the construction process was a distinguishing factor, noting that they at least consented to the project and allowed the contractors to work on their property. The court determined there was not such a “lack of privity” that plaintiffs’ claims should “not fall under the general rule of accrual” articulated in *Newburgh*.
The Court also addressed the municipalities’ argument that the continuing presence of roadway defects constituted a continuing public nuisance, giving rise to successive causes of action. The Court disagreed, stating that the contractors’ tortious conduct consisted of discrete acts of negligence that ceased upon completion of the sewer construction. “Although plaintiffs allege that the injuries to their property are ongoing, defendants’ tortious conduct consisted of discrete acts (i.e., negligent excavation and backfilling) that ceased upon completion of the sewer construction over 20 years ago.” The court distinguished this situation from cases involving an unlawful encroachment or continuous interference with property easements. Because the municipalities commenced the actions more than three years after the contractors completed the construction work, these claims were also time-barred.