Grow Construction Co., Inc. v. State, 56 N.Y.2d 914 (1982)
When a state’s interference with a subcontractor’s work on a project causes increased costs, the general contractor, acting on behalf of the subcontractor, can recover damages from the state based on quantum meruit, calculated as actual job cost plus overhead and profit, less amounts already paid.
Summary
Grow Construction Co., the general contractor for a highway improvement project, sued the State on behalf of its subcontractor, D. Lambert Railing Co., alleging breach of contract due to the State’s interference with Lambert’s guide rail work. The Court of Claims found the State liable, and the Appellate Division affirmed. The Court of Appeals affirmed, holding that the State’s interference disrupted Lambert’s work schedule, increasing costs. Damages were properly calculated on a quantum meruit basis, representing the reasonable value of Lambert’s work performed: actual job cost, plus overhead and profit, minus payments already made. The State had the opportunity to present evidence to reduce damages at the Court of Claims.
Facts
D. Lambert Railing Co. was subcontracted to handle the guide rail work for a Cross Westchester Parkway improvement project. A dispute arose between Lambert and the State’s engineer-in-chief regarding preparatory work and the nature of the guide rail work itself. The State interfered with Lambert’s work, causing severe disruptions to the work schedule and resulting in increased costs for Lambert.
Procedural History
Grow Construction Co., acting on behalf of Lambert, sued the State in the Court of Claims. The Court of Claims found the State liable for breach of contract. The Appellate Division affirmed the Court of Claims’ decision regarding liability and the calculation of damages. The State appealed to the Court of Appeals.
Issue(s)
Whether the State’s interference with the subcontractor’s work constituted a breach of contract, entitling the general contractor to damages on behalf of the subcontractor. Whether the damages were properly calculated on a quantum meruit basis, reflecting the reasonable value of the work performed.
Holding
Yes, because the State’s interference caused severe disruption in Lambert’s work schedule and resulted in increased costs, constituting a breach of contract. Yes, because damages were appropriately measured on a quantum meruit basis, including actual job cost plus allowance for Lambert’s overhead and profit, less amounts already paid.
Court’s Reasoning
The Court of Appeals affirmed the lower courts’ findings regarding the State’s liability, noting that these findings were supported by the record and thus beyond their review. The court agreed with the Appellate Division’s calculation of damages based on quantum meruit. The court stated that Grow Construction, seeking the reasonable value of the work performed by Lambert, was entitled to recover damages measured as actual job cost plus allowance for Lambert’s overhead and profit minus the amounts thus far paid. Citing D’Angelo v State of New York, 41 AD2d 77, 80, the court emphasized that quantum meruit is the appropriate measure when seeking the value of work actually performed. The court highlighted that the State had the opportunity to submit proof to reduce the amount of damages before the Court of Claims but failed to do so. The holding emphasizes that when the state interferes with contract work, the contractor is entitled to be compensated for the actual value of the work performed, reflecting a practical approach to ensuring fair compensation in construction disputes.