Sisters of St. John the Baptist, Providence Rest Convent v. Geraghty Constructor, Inc., 67 N.Y.2d 997 (1986)
When a broad arbitration clause exists in a contract, disputes relating to extra work allegedly authorized and required for the completion of the contract fall within the scope of the arbitration clause, even if the extra work is claimed to be outside the original scope of the agreement.
Summary
Sisters of St. John the Baptist (Petitioner) contracted with Geraghty Constructor, Inc. (Respondent) for convent renovations. A dispute arose over cost overruns, with Respondent claiming the work was outside the original contract and demanding arbitration. Petitioner sought to stay arbitration, arguing the work wasn’t authorized. The Court of Appeals held that the dispute fell within the broad arbitration clause covering disputes “arising out of, or relating to, the Contract Documents”. The court emphasized that the arbitration clause applied not only to the original agreement but also to modifications and changes, making arbitration the proper forum for resolving the dispute.
Facts
Respondent contracted with Petitioner to renovate a convent for a stipulated sum, with allowances for changes. The contract contained a broad arbitration clause for all disputes arising from the contract. As renovations progressed, modifications were made due to unforeseen conditions. Respondent submitted payment applications, receiving a substantial amount for labor and materials. A dispute arose concerning cost overruns; Respondent claimed that certain labor and materials were outside the scope of the agreement and demanded arbitration for the unpaid balance.
Procedural History
Respondent filed a notice of intention to arbitrate. Petitioner sought a stay of arbitration. Special Term granted the stay, which the Appellate Division affirmed. The New York Court of Appeals reversed the Appellate Division’s order, denying the stay of arbitration.
Issue(s)
Whether a dispute over extra work allegedly authorized and required for the completion of a construction contract falls within the scope of a broad arbitration clause in that contract, even if the extra work is claimed to be outside the original scope of the agreement.
Holding
Yes, because the arbitration clause provided broadly for arbitration of all disputes “arising out of, or relating to, the Contract Documents,” and those documents included not only the original agreement and plans but also later modifications and written changes. Given these defined terms, disputes relating to extra work allegedly authorized and required for execution and completion of respondent’s renovation of the convent arise out of or relate to the “Contract Documents” and thus fall generally within the arbitration clause.
Court’s Reasoning
The court emphasized that its role is limited to determining whether the parties agreed to arbitrate and whether the dispute falls within the scope of the arbitration agreement. The court’s inquiry ends once it establishes a relationship between the dispute’s subject matter and the underlying agreement to arbitrate. Interpretation of specific contract terms is left to the arbitrators.
The court noted that the arbitration clause was broad, encompassing all disputes “arising out of, or relating to, the Contract Documents.” The “Contract Documents” included not only the original agreement but also later modifications and written changes. The court reasoned that disputes over extra work, even if outside the original agreement’s scope, still relate to the “Contract Documents” because the parties provided for “changes in the scope of work.”
The court addressed the lower courts’ reliance on the Respondent’s statement that some work was outside the original agreement, clarifying that the possibility of changes in the scope of work brought it under the arbitration clause. The court also stated that submitting to arbitration did not equate to acknowledging liability for costs exceeding the stipulated sum.
The court directly quoted the contract language to support its conclusion: “The Work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction.”