805 Third Ave. Co. v. M.W. Realty Associates, 58 N.Y.2d 447 (1983)
A claim of economic duress in contract modification requires demonstrating that one party wrongfully threatened to breach the original agreement by withholding a legally required performance unless the other party agreed to further demands.
Summary
805 Third Avenue Co. sued M.W. Realty Associates seeking to rescind a modified contract for the sale of air rights, claiming economic duress. 805 Third Ave. Co. alleged that M.W. Realty Associates wrongfully refused to deliver documents required under the original contract unless 805 Third Ave. Co. agreed to a modification more favorable to M.W. Realty Associates. The New York Court of Appeals affirmed the dismissal of the complaint, holding that because 805 Third Ave. Co. failed to fulfill its preconditions for M.W. Realty Associates’ performance under the original agreement, M.W. Realty Associates’ refusal to deliver the documents was not a wrongful act constituting economic duress. The court emphasized that a party cannot be guilty of economic duress for refusing to do something it is not legally required to do.
Facts
805 Third Avenue Co., a ground lessee, contracted with M.W. Realty Associates to purchase air rights for $1.9 million to construct a 31-story building. The agreement, dated September 18, 1979, stipulated that 805 Third Avenue Co. would deposit cash and a promissory note in escrow, while M.W. Realty Associates would deposit a declaration of zoning lot restrictions and a single lot and easement agreement. These escrow deposits were to be exchanged on the “Sales Closing Date”, defined as the date a building permit was issued or when excavation or construction began for the proposed building. 805 Third Avenue Co. began foundation work on December 4, 1979, after obtaining a permit for the foundation only. In May 1980, 805 Third Avenue Co. demanded delivery of the documents, but M.W. Realty Associates refused unless 805 Third Avenue Co. agreed to modify the contract to terms more favorable to M.W. Realty Associates. 805 Third Avenue Co. then executed the modified contract, claiming economic duress.
Procedural History
805 Third Avenue Co. sued M.W. Realty Associates to rescind the modified contract, claiming economic duress. Special Term granted a preliminary injunction maintaining the status quo and denied M.W. Realty Associates’ motion to dismiss. The Appellate Division modified the order by vacating the injunction and granting the motion to dismiss. The Court of Appeals then reviewed the Appellate Division’s order.
Issue(s)
Whether M.W. Realty Associates’ refusal to deliver documents under the original contract, absent 805 Third Avenue Co.’s fulfillment of its preconditions, constituted a wrongful threat amounting to economic duress that would justify rescission of the modified contract.
Holding
No, because 805 Third Avenue Co. failed to fulfill the preconditions for M.W. Realty Associates’ performance under the original contract, M.W. Realty Associates’ refusal to deliver the documents was not a wrongful act and therefore did not constitute economic duress.
Court’s Reasoning
The court found that the contract of September 18, 1979, annexed to the complaint, governed the obligations of the parties. According to the contract, M.W. Realty Associates was only obligated to deliver the declaration and lot agreement on the “Sales Closing Date,” which the contract defined as the date of the building permit’s issuance or the commencement of construction. Because 805 Third Avenue Co. began construction on December 4, 1979, the Sales Closing Date was triggered. The court determined that delivery of the declaration and lot agreement was conditioned on 805 Third Avenue Co. delivering (a) the cash down payment and promissory note, plus interest, (b) a letter of credit securing payment of the balance, and (c) the architectural drawings. Since 805 Third Avenue Co. failed to plead that it fulfilled these conditions, M.W. Realty Associates was under no legal duty to deliver the documents. The court stated, “a party cannot be guilty of economic duress for refusing to do that which it is not legally required to do.” The court distinguished this case from others where the plaintiff’s pleading was sufficient on its face but the right to recovery was doubtful, noting that this action was controlled by the contract annexed to the complaint and that there was no factual dispute, only a legal one concerning the instrument’s interpretation. The court relied on the principle that contract interpretation is a legal matter for the court, and the contract provisions prevail over conclusory allegations in the complaint.