X.L.O. Concrete Corp. v. Brady & Co., 666 N.E.2d 178 (N.Y. 1996)
A liquidated damages clause for delay in completion does not apply when the contractor abandons the project completely unless the clause contains clear and unambiguous language stating that it applies even in the event of abandonment.
Summary
X.L.O. Concrete Corp. sued Brady & Co. for breach of contract after Brady abandoned a municipal parking garage construction project before completion. X.L.O. sought actual and liquidated damages based on a clause specifying $1,000 per day for delay in completion. The New York Court of Appeals held that the liquidated damages clause, which addressed delays, did not apply to Brady’s outright abandonment because the clause lacked clear language indicating its applicability in such an event. The court reasoned that absent specific contractual language, a liquidated damages provision for delay is unenforceable when a contract is completely renounced.
Facts
Brady & Co. contracted with X.L.O. Concrete Corp. to construct a municipal parking garage. Disputes arose during construction regarding progress payments, leading Brady to discontinue work five months before the scheduled completion date. X.L.O. hired another contractor to finish the project, resulting in a delay in the garage’s opening. The contract included a liquidated damages clause specifying $1,000 per day for any delay in completing the work, stating that actual damages for delay were impossible to determine.
Procedural History
Following arbitration, X.L.O. sued Brady for breach of contract, seeking both actual and liquidated damages. The trial court found Brady liable for breach of contract and awarded both actual and liquidated damages. The Appellate Division modified the judgment, subtracting the liquidated damages award. The New York Court of Appeals granted review to determine the enforceability of the liquidated damages clause.
Issue(s)
Whether a liquidated damages clause for delay in completing work is enforceable when the contractor abandons the project before completion, where the clause does not explicitly state that it applies in the event of abandonment.
Holding
No, because the liquidated damages clause lacked clear and unambiguous language indicating that it was intended to apply to the contractor’s outright abandonment of the project, an eventuality distinct from mere delay.
Court’s Reasoning
The court emphasized that liquidated damages clauses must contain clear and unambiguous language to be enforceable, especially when applied to situations beyond their explicit terms. The court likened the case to Murphy v United States Fid. & Guar. Co., stating that the liquidated damages provision only applied until the contractor had fulfilled its agreement, not when there was a complete renunciation of the contract. The court reasoned that the clause specifically addressed delays in completion, not a complete abandonment of the project. While the court acknowledged X.L.O.’s concern that this interpretation could incentivize contractors to abandon projects to avoid liquidated damages, it noted that owners can protect themselves by including express provisions for liquidated damages that apply even in the event of abandonment. The court stated that “[t]he only reasonable interpretation which can be given to [the liquidated damage] provision is * * * that the liability for the stipulated sum did not accrue until the contractor had fulfilled [its] agreement.”