Matter of Parkview Assoc. v. City of N.Y., 1 N.Y.3d 682 (2004)
A case challenging a construction project is moot when the project is substantially complete and the challenger failed to seek preliminary injunctive relief to preserve the status quo during litigation.
Summary
Parkview Associates challenged the issuance of a certificate of appropriateness (COA) for a construction project, arguing that it required environmental review under SEQRA. They did not seek a preliminary injunction to halt construction. By the time the case reached the Court of Appeals, the project was substantially complete. The Court of Appeals held the appeal was moot because the project was nearly finished, demolishing the work would cause undue hardship, and the challengers failed to seek preliminary injunctive relief to prevent construction during the litigation. This highlights the importance of seeking preliminary injunctions to preserve legal challenges to ongoing projects.
Facts
The New York City Landmarks Preservation Commission approved a proposal to construct an eight-story building on an existing one-story building. Parkview Associates commenced a CPLR article 78 proceeding to annul the COA, arguing it required compliance with SEQRA. Construction began, and Parkview Associates did not seek a temporary restraining order or preliminary injunction to halt the work. By the time the case reached the Court of Appeals, the building’s steel and concrete structure, brick facade, and most window frames were complete, with roughly $25.7 million already spent on the project.
Procedural History
Supreme Court denied the petition and dismissed the proceeding. The Appellate Division affirmed. The Court of Appeals granted leave to appeal.
Issue(s)
Whether the appeal should be dismissed as moot given the substantial completion of the construction project and the petitioners’ failure to seek preliminary injunctive relief.
Holding
Yes, because the construction project was substantially complete, demolishing portions would cause undue hardship, and the petitioners failed to seek preliminary injunctive relief to preserve the status quo during the litigation.
Court’s Reasoning
The Court of Appeals applied the mootness doctrine, noting that a change in circumstances prevented the court from rendering an effective decision. Regarding construction projects, the court considers the progress of the work, but a “race to completion cannot be determinative.” Crucially, the court emphasized the challenger’s failure to seek preliminary injunctive relief or otherwise preserve the status quo. The court found that the project was substantially complete, and reducing the building’s height would “inevitably alter the proportion, mass and details of a design that the Commission determined would fit in with the special architectural and historic character of the district.” Furthermore, the court rejected the argument that the property owner engaged in an “unseemly race to completion,” noting they had every business incentive to complete the project quickly. The court stated that the petitioners “were required, at a minimum, to seek an injunction in the circumstances presented here.” Finally, the court found the exception to the mootness doctrine inapplicable because the issues were likely to recur with adequate opportunity for review if objectors promptly requested injunctive relief. As the court pointed out, those challenging a COA on SEQRA grounds can protect against mootness by promptly requesting injunctive relief.