48 N.Y.2d 127 (1979)
A surety company, by incorporating a subcontract with a broad arbitration clause into its performance bond, agrees to be bound by the arbitration of disputes arising under the subcontract between the general contractor and the subcontractor, but does not necessarily agree to arbitrate separate disputes arising directly under the performance bond itself.
Summary
Parsons & Whittemore (P&W), a general contractor, subcontracted with Central Rigging, which furnished a performance bond from Fidelity and Deposit Company (Fidelity). The subcontract included a broad arbitration clause. When a dispute arose, P&W demanded arbitration against both Central and Fidelity. Fidelity sought a stay of arbitration, arguing it never agreed to arbitrate. The court held that Fidelity was bound by the arbitration clause in the subcontract (incorporated into the bond) regarding disputes *between* P&W and Central. However, Fidelity did not agree to arbitrate disputes arising *directly* under the performance bond itself. Therefore, the stay of arbitration was denied for the underlying subcontract dispute but upheld for any separate claims arising solely under the bond. The court emphasized the intention of the parties and the practical implications of resolving the principal’s liability (Central) and the surety’s liability (Fidelity) in separate forums.
Facts
- Parsons & Whittemore (P&W) was the general contractor for a building construction project.
- P&W subcontracted with Central Rigging and Contracting Corporation (Central).
- The subcontract required Central to furnish a performance bond and contained a clause requiring arbitration of disputes arising out of the contract.
- Central obtained a performance bond from Fidelity and Deposit Company of Maryland (Fidelity), which incorporated the subcontract by reference.
- A dispute arose between P&W and Central regarding Central’s performance.
- P&W demanded arbitration against both Central and Fidelity.
- Fidelity sought a stay of arbitration, arguing it had not agreed to arbitrate.
Procedural History
- Special Term granted Fidelity’s application to stay arbitration.
- The Appellate Division affirmed.
- The Court of Appeals granted leave to appeal.
Issue(s)
- Whether, by incorporating a subcontract containing an arbitration clause into its performance bond, the surety company (Fidelity) agreed to arbitrate disputes arising under the subcontract between the general contractor (P&W) and the subcontractor (Central).
- Whether the surety company (Fidelity) agreed to arbitrate separate and distinct controversies arising under the terms of the performance bond itself between the general contractor (P&W) and the surety company (Fidelity).
Holding
- Yes, because the surety company accepted the agreement of the general contractor and the subcontractor that disputes between them would be settled by arbitration; an implicit corollary of that acceptance was agreement by the surety company that for purposes of later determining its liability under its performance bond, it would accept and be bound by the resolution reached in the arbitration forum.
- No, because there was no agreement on the part of any party that controversies arising as to rights and obligations under the terms of the performance bond would be submitted to arbitration.
Court’s Reasoning
The court reasoned that by incorporating the subcontract into the performance bond, Fidelity agreed to be bound by the resolution of disputes between P&W and Central reached through arbitration. The court emphasized that the subcontract contained an express agreement to arbitrate disputes arising under it. However, this incorporation did not extend to requiring Fidelity to arbitrate separate disputes arising *directly* under the performance bond. The court distinguished between disputes relating to Central’s performance of the subcontract (which are subject to arbitration with Fidelity bound by the outcome) and disputes regarding Fidelity’s obligations under the performance bond itself (which are not subject to arbitration unless the bond explicitly provides for it). The court stated, “Although it did not agree to participate in any arbitration, it did accept the agreement of the general contractor and the subcontractor that disputes between them would be settled by arbitration. An implicit corollary of that acceptance was agreement by the surety company that for purposes of later determining its liability under its performance bond, it would accept and be bound by the resolution reached in the arbitration forum.” The court overruled Matter of Lehman v Ostrovsky to the extent it conflicted with this holding. Chief Judge Cooke dissented in part, arguing that the incorporation of the subcontract required Fidelity to be a party to the arbitration concerning Central’s alleged breach, and not just be bound by the outcome. The dissent emphasized the language of the arbitration clause, which states that “[a]ll disputes arising out of this Contract, its interpretation, performance or breach, shall be submitted to arbitration”.