Tufano Contracting Corp. v. State, 256 N.E.2d 427 (N.Y. 1970)
r
r
When a contract contains specific provisions and a general ‘catch-all’ clause, the specific provisions govern; however, a state may waive a contractual provision regarding waiver of interest by stipulating in court to reserve the interest question until the resolution of other claims.
r
r
Summary
r
Tufano Contracting Corp. sued the State of New York for additional payments beyond the final payment tendered for work completed under a contract. The dispute centered on claims for Portland cement, temporary sheet piling, and interest on the final payment. The Court of Appeals addressed whether Tufano was entitled to payment for materials used outside the contract’s neat lines, for sheet piling exceeding the estimated quantity, and whether the State waived a contract provision regarding interest. The Court held Tufano was not entitled to payment for the cement or excess sheet piling due to specific contract provisions, but the State had waived the interest provision through a stipulation in court. This case highlights the importance of specific contract terms over general clauses and the potential for parties to waive contractual rights through their conduct in litigation.
r
r
Facts
r
Tufano Contracting Corp. entered into a contract with the New York State Department of Public Works for construction work. The contract included plans, a proposal form, and a book of general specifications. After completing the work, Tufano sought additional payment for: (1) Portland cement used to replace rock excavated beyond the specified lines (“neat lines”); (2) temporary steel sheet piling exceeding the estimated quantity; and (3) interest on the final payment which was initially refused by Tufano.
r
r
Procedural History
r
Tufano sued in the Court of Claims, seeking the final payment and additional compensation. The Court of Claims ruled in favor of Tufano on several claims. The State appealed to the Appellate Division regarding the allowances for Portland cement, temporary sheet piling, and interest. The Appellate Division reversed the Court of Claims on all three points. Tufano then appealed to the New York Court of Appeals.
r
r
Issue(s)
r
1. Whether Tufano was entitled to payment for Portland cement used to replace excavation outside the contract’s designated “neat lines,” given a contract provision requiring such replacement at the contractor’s expense?
r
2. Whether Tufano was entitled to payment for temporary steel sheet piling exceeding the estimated quantity in the contract, considering specific contract provisions limiting payment to the estimated quantity or approved field changes?
r
3. Whether the State waived the contract provision stipulating that refusal of final payment constitutes a waiver of interest, by stipulating in court to reserve the interest question until resolution of other claims?
r
r
Holding
r
1. No, because the contract specifically stated that any excavation outside the “neat lines” had to be replaced with concrete at the contractor’s expense.
r
2. No, because the contract’s measurement and payment provision applied only when plans did not specify how to determine the square footage area for payment, and Tufano was already paid for all steel piling placed in its planned position.
r
3. Yes, because by stipulating to reserve the interest question, the State waived the contract provision, especially since Tufano successfully established rights to additional money.
r
r
Court’s Reasoning
r
Regarding the Portland cement, the Court relied on the explicit contract provision that excavation outside the